The Southampton to London Pipeline Development Consent Order 2020

JurisdictionUK Non-devolved

2020 No. 1099

Infrastructure Planning

The Southampton to London Pipeline Development Consent Order 2020

Made 7th October 2020

Coming into force 29th October 2020

An application has been made to the Secretary of State under section 37 of the Planning Act 20081(“the 2008 Act”) and in accordance with the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 20092for an Order granting development consent.

The application was examined by a panel of four members (“the Panel”) (appointed by the Secretary of State) in accordance with Chapter 4 of Part 6 of the 2008 Act, and the Infrastructure Planning (Examination Procedure) Rules 20103.

The Panel, having considered the representations made and not withdrawn and the application together with the accompanying documents, in accordance with section 74 of the 2008 Act, has submitted a report with a recommendation to the Secretary of State.

The Secretary of State, has considered the representations made and not withdrawn, the report of the Panel and the environmental information in accordance with regulation 4 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 20174and has had regard to the documents and matters referred to in section 104(2) of the 2008 Act.

The Secretary of State having decided the application has determined to make an Order granting development consent for the development described in the application on terms which in the opinion of the Secretary of State are not materially different to the proposals comprised in the application.

The Secretary of State is satisfied that the parcels of common, open space or fuel or field allotment land comprised within the Order limits (as identified in the Book of Reference), when burdened with rights imposed by this Order, will be no less advantageous than they were before to persons in whom they are vested, other persons, if any, entitled to rights of common or other rights and the public, and that accordingly, section 132(3) of the 2008 Act applies.

The Secretary of State, in exercise of the powers conferred by sections 114, 115 and 120 of the 2008 Act, makes the following Order—

1 PRELIMINARY

PART 1

PRELIMINARY

S-1 Citation and commencement

Citation and commencement

1. This Order may be cited as the Southampton to London Pipeline Development Consent Order 2020 and comes into force on 29th October 2020.

S-2 Interpretation

Interpretation

2.—(1) In this Order—

the 1961 Act” means the Land Compensation Act 19615;

the 1965 Act” means the Compulsory Purchase Act 19656;

the 1980 Act” means the Highways Act 19807;

“the 1981 Act” means the Compulsory Purchase (Vesting Declarations) Act 19818;

“the 1984 Act” means the Road Traffic Regulation Act 19849;

“the 1990 Act” means the Town and Country Planning Act 199010;

“the 1991 Act” means the New Roads and Street Works Act 199111;

the 2008 Act” means the Planning Act 200812;

“the 2016 Regulations” means the Environmental Permitting (England and Wales) Regulations 201613;

“access & rights of way plan” means the plans of that description set out in Schedule 11 (documents to be certified) and certified by the Secretary of State as the access & rights of way plan for the purposes of this Order;

“address” includes any number or address for the purposes of electronic transmission;

“apparatus”, unless otherwise provided for, has the same meaning as in Part 3 of the 1991 Act;

“authorised development” means the development and associated development described in Schedule 1 (authorised development) or any part of it, which is development within the meaning of section 32 (meaning of development) of the 2008 Act;

“the book of reference” means the document of that description set out in Schedule 11 (documents to be certified) and certified by the Secretary of State as the book of reference for the purposes of this Order;

“building” includes any structure or erection or any part of a building, structure or erection;

“business days” means Monday to Friday excluding Bank Holidays and other public holidays or days on which general or local elections are held;

“carriageway” has the same meaning as in the 1980 Act and includes part of a carriageway;

“CEMP” means the construction environmental management plan to be prepared and approved under Requirement 6 (construction environmental management plan) of Schedule 2 (Requirements);

“code of construction practice” means the document of that description set out in Schedule 11 (documents to be certified) and certified by the Secretary of State as the code of construction practice for the purposes of this Order;

“commence” means the carrying out of any material operation (as defined in section 155 of the 2008 Act) forming part, or carried out for the purposes, of the authorised development other than operations consisting of remediation works, environmental (including archaeological) surveys and investigation, site or soil survey, erection of fencing to site boundaries or marking out of site boundaries, installation of amphibian and reptile fencing, the diversion or laying of services or environmental mitigation measures, and “commencement” must be construed accordingly;

“cycle track” has the same meaning as in the 1980 Act and includes part of a cycle track14;

“electronic transmission” means a communication transmitted—

(a) by means of an electronic communications network; or

(b) by other means but while in electronic form;

“environmental statement” means the environmental statement (May 2018 – Documents 6.1 to 6.4) as submitted by Esso Petroleum Company, Limited to support its application for development consent;

“footway” and “footpath” have the same meaning as in the 1980 Act and include part of a footway or footpath;

“the general arrangement plans” means the plans of that description set out in Schedule 11 (documents to be certified) and certified as the general arrangement plans by the Secretary of State for the purposes of this Order;

“highway”, “highway authority” and “local highway authority” have the same meaning as in the 1980 Act and “highway” includes part of a highway;

“the land plans” means the plans of that description set out in Schedule 11 (documents to be certified) and certified as the land plans by the Secretary of State for the purposes of this Order;

“limits of deviation” means the limits of deviation referred to in article 6 (limits of deviation) and shown on the works plans;

“maintain” in relation to the authorised development includes to inspect, assess, repair, test, cleanse, adjust, alter, divert, renew, re-lay, improve, landscape, preserve, make safe, dismantle, remove, clear, reconstruct, refurbish, replace, demolish, abandon or decommission any part of the authorised development, provided such works do not give rise to any materially new or materially different environmental effects to those identified in the environmental statement and for the avoidance of doubt must not include the renewal, re-laying, reconstruction or replacement of the entirety of the pipeline works, and any derivative of “maintain” is to be construed accordingly;

“Ministry of Justice Land” means all land where the Secretary of State for Justice has an interest including plots 2043, 2044, 2045, 2052, 2057, 2060, 2061, 2063 and 2067 as set out in Part 4 of the book of reference;

“Order land” means the land shown on the land plans which is within the limits of land to be acquired or used permanently or temporarily, and described in the book of reference;

“the Order limits” means the limits of lands to be acquired or used permanently or temporarily shown on the land plans and works plans within which the authorised development may be carried out;

“owner”, in relation to land, has the same meaning as in section 7 of the Acquisition of Land Act 1981 (interpretation)15;

“the permit schemes” mean the following schemes made under Part 3 of the Traffic Management Act 200416as in force at the date on which this Order is made—

(a) the Traffic Management (Hampshire County Council) Permit Scheme Order 2019; and

(b) the Traffic Management (Surrey County Council) Permit Scheme Order 2015 (as varied);

“the pipeline works” means Works Nos. 1A to 1H (inclusive) as set out in Schedule 1 (authorised development) excluding any pipeline marker posts and cathodic protection test posts;

“relevant highway authority” means, in any given provision of this Order (including the Requirements), the local highway authority for the area to which the provision relates;

“relevant planning authority” means, in any given provision of this Order (including the Requirements), the local planning authority—

(a) for the area of land to which the provision relates is situated; and

(b) with the relevant legislative competence under the 1990 Act for the matter to which that provision relates;

“Requirements” means the requirements listed in Part 1 of Schedule 2 (requirements), and any reference to a numbered requirement is to be construed accordingly;

“statutory undertaker” means any statutory undertaker for the purposes of section 127(8), of the 2008 Act (statutory undertakers’ land) and includes a public communications provider as defined in section 151(1) of the Communications Act 200317;

“street” means, irrespective of whether it is a thoroughfare, the whole or any part of any highway, road, lane, footway, alley, passage, square, court and any land laid out as a way, whether it is for the time being formed as a footpath or not, together with land on the verge of a street or between two carriageways, and includes part of a street and any bridge, viaduct, overpass or underpass which a street passes over;

“street authority”, in relation to a street, has the same meaning as in Part 3 (street works in England and Wales) of the 1991 Act;

“traffic authority” has the same meaning as in the 1984 Act;

“undertaker” means Esso Petroleum Company, Limited (Company No. 00026538) of Ermyn House, Ermyn Way...